Improving Access to reliable on Grid Electricity Services for Households and Priority public institutions - BE2EARP

Project Category Low Voltage , Medium Voltage
Project Name Improving Access to reliable on Grid Electricity Services for Households and Priority public institutions - BE2EARP
Donor/Funder Belgian funds
Effectiveness Date 17 Dec 2015
Closure Date 16 Dec 2019
Status Completed

Scope

  • Grid extension (129 km of MV, 213km of LV and 8,119 connections)
  • Beneficiaries (households, productive- and community uses) are supported in improving their access level
  • Coherence and coordination are improved between EARP and other energy access initiatives

Geographic Coverage

--

Photos

Official REG energy infrastructure
Public summary
Improving Access to reliable on Grid Electricity Services for Households and Priority public institutions - BE2EARP information published by Rwanda Energy Group.
Project category
Low Voltage , Medium Voltage
Project status
Completed
Donor / funder
Belgian funds
Project scope
  • Grid extension (129 km of MV, 213km of LV and 8,119 connections)
  • Beneficiaries (households, productive- and community uses) are supported in improving their access level
  • Coherence and coordination are improved between EARP and other energy access initiatives