Methane Gas in Rwanda
Methane Gas Resources is found in the Lake Kivu in the Eastern African Rift Zone. The lake contains high concentrations of naturally occurring methane gas (CH4) and carbon dioxide (CO2), with the highest concentrations at depths ranging from 270m to 500m at an area of around 2,400 sq.km.
The oxygenated upper layer of the lake from the surface to a depth of 60m supports the lake’s biology. The resource is equally shared between Rwanda and the Democratic Republic of Congo.
Until 2004, extraction of the gas was done on a small scale, with the extracted gas being used to run boilers at a brewery in Gisenyi. Since then, the Government of Rwanda has prioritized the production of electricity from this unique resource in order to address the growing electrical energy deficit.
Completed and Ongoing Methane-to-Power Projects
a) KivuWatt project, a subsidiary of Contour Global (US-based Company) entered into commercial operations since 31st December 2015 and operates at base load with a nominal gross capacity of 26 MW.
c) Shema Power Lake Kivu Ltd, signed a 25-year power purchase agreement (PPA) with the Rwanda Energy Group (REG) for a 56 MW net power output from methane gas. The Power plant is located on Nyamyumba sector in Rubavu District. Currently the power plant is generating 37.5 MW and will soon reach its full capacity.
Project List
Related Projects
110kV Jabana-Mt. Kigali-Gahanga and associated substations
The project consists of building a 27km long 110KV transmission line linking Jabana, Mont Kigali up to Gahanga Substation.
View project110 kV Gasogi-KSEZ
The project consists of building a 2.2km long 110KV transmission line linking Gasogi substation to Kigali Special Economic Zone
View project110 kV Single Circuit: Mukungwa-Nyabihu
The project consists of construction of 29km long transmission line linking Mukungwa to Nyabihu
View project220 KV Bwishyura-Kigoma-Rwabusoro
The project consists of building a 62 km long 220KV transmission line linking Bwishyura, Kigoma and Rwabusoro.
View project110 kV Rukarara-Kilinda
This is 110 KV transmission line with a length of 31.5km. It evacuates power from Rukarara Hydropower plant to Kilinda Substation
View project220/110 kV Mamba-Rwabusoro-(110kV) Bugesera- Gahanga
The project consists of building a 84.5 km long transmission line evacuating power from Hakan Peat to Power plant in Gisagara District up to Gahanga in through Rwabusoro and Bugesera substations