Official page content
110kV Jabana-Mt. Kigali-Gahanga and associated substations
| Project Category | Transmission |
| Project Name | 110kV Jabana-Mt. Kigali-Gahanga and associated substations |
| Donor/Funder | Government of Rwanda & European Union |
| Effectiveness Date | 01 Jul 2016 |
| Closure Date | 01 Jan 2019 |
| Status | Completed |
Scope
The project consists of building a 27km long 110KV transmission line linking Jabana, Mont Kigali up to Gahanga Substation.
Geographic Coverage
Jabana - Mont Kigali - Gahanga
Public summary
The project consists of building a 27km long 110KV transmission line linking Jabana, Mont Kigali up to Gahanga Substation.
Project category
Transmission
Project status
Completed
Donor / funder
Government of Rwanda & European Union
Project scope
The project consists of building a 27km long 110KV transmission line linking Jabana, Mont Kigali up to Gahanga Substation.
Effectiveness date
Closure date
Geographic coverage
Jabana - Mont Kigali - Gahanga
Official project image
110kV Jabana-Mt. Kigali-Gahanga and associated substations