Kigali Network Strenghening 1 - 1
| Project Category | Transmission , Medium Voltage |
| Project Name | Kigali Network Strenghening 1 - 1 |
| Donor/Funder | EUCL |
| Effectiveness Date | 01 Jun 2016 |
| Closure Date | 28 Feb 2017 |
| Status | Completed |
Scope
Improved stability of power supply in Bugesera and parts of Kigali by replacing a10MVA transformer by a 20MVA at Mont Kigali substation
Geographic Coverage
Nyarugenge-Bugesera-Kamonyi
Public summary
Improved stability of power supply in Bugesera and parts of Kigali by replacing a10MVA transformer by a 20MVA at Mont Kigali substation
Project category
Transmission , Medium Voltage
Project status
Completed
Donor / funder
EUCL
Project scope
Improved stability of power supply in Bugesera and parts of Kigali by replacing a10MVA transformer by a 20MVA at Mont Kigali substation