Official page content

Kigali Network Strenghening 1 - 2

Project Category Medium Voltage
Project Name Kigali Network Strenghening 1 - 2
Donor/Funder EUCL
Effectiveness Date 01 Aug 2016
Closure Date 31 May 2018
Status Completed

Scope

Kigali distribution network reinforced (upgrade, rehabilitation and integration to SCADA of 6 identified substations )

Geographic Coverage

Rugende; Rubungo; Kacyiru; Pilone 20; Mumena and Centre Christus

Photos

Official REG energy infrastructure
Public summary
Kigali distribution network reinforced (upgrade, rehabilitation and integration to SCADA of 6 identified substations )
Project category
Medium Voltage
Project status
Completed
Donor / funder
EUCL
Project scope
Kigali distribution network reinforced (upgrade, rehabilitation and integration to SCADA of 6 identified substations )
Effectiveness date
Closure date
Geographic coverage
Rugende; Rubungo; Kacyiru; Pilone 20; Mumena and Centre Christus
Official project image
Official REG What We Do image