What We Do

Generation

Currently,the installed capacity increased by 53 MW, from 353.402MW in FY 2022/2023 to 406.402MW in 2023/2024. This includes 56MW from the commissioning of Shema plant and 27 MW from the Rusumo plant. Additionally, 30MW was decommissioned from SOEnergy by January 2024.

Generation at a Glance

406.402 MW

Installed generation capacity

FY 2023/2024

332.6 MW

Installed generation capacity (legacy page value)

Reporting period not stated

472.95 MW

Installed generation capacity

June 2026

Overview

Currently,the installed capacity increased by 53 MW, from 353.402MW in FY 2022/2023 to 406.402MW in 2023/2024. This includes 56MW from the commissioning of Shema plant and 27 MW from the Rusumo plant. Additionally, 30MW was decommissioned from SOEnergy by January 2024.

List of Power Plants

As part of the efforts to increase the current capacity, a number of projects to build new power plants are underway and will add more capacity on the existing national grid by the year 2024. These include among others Hakan peat to power plant which will add 80MW, Rusumo Falls Hydropower plant (26MW), Rusizi III (48.3MW), Shema (56 MW) and Nyabarongo II (43.5 MW). 

These projects are expected to considerably reduce the usage of expensive sources (fuel) and change the generation technology mix as indicated in the graph below:

Official REG energy infrastructure

Currently, the total installed capacity to generate electricity in Rwanda is 332.6 MW from different power plants. By generation technology mix, 51% is from thermal sources, followed by hydro sources (43.9%) and solar sources with 4.2%. 

List of Power Plants

As part of the efforts to increase the current capacity, a number of projects to build new power plants are underway and will add more capacity on the existing national grid by the year 2024. These include among others Hakan peat to power plant which will add 80MW, Rusumo Falls Hydropower plant (26MW), Rusizi III (48.3MW), Shema (56 MW) and Nyabarongo II (43.5 MW).

Energy Sources

Hydropower

Over the last decade, Rwanda’s hydropower sector showed a tremendous progress. Overall installed capacity of power is about 390.04MW, hydropower contributing 39.6% of it.

Explore

Solar

With a potential of 4.5 kWh per m2 per day and approximately 5 peak sun hours, solar energy has a huge potentiality in Rwanda. Currently, Rwanda’s total on-grid installed solar energy is 12.050 MW originating from 3 solar power plants namely Jali power plant generating 0.25MW, Rwamagana Gigawatt generating 8.5 MW, and the Nasho Solar plant generating 3.3 MW.

Explore

Methane Gas

Methane Gas Resources is found in the Lake Kivu in the Eastern African Rift Zone. The lake contains high concentrations of naturally occurring methane gas (CH4) and carbon dioxide (CO2), with the highest concentrations at depths ranging from 270m to 500m at an area of around 2,400 sq.km.

Explore

Peat

Rwanda peat study indicate that Rwandan peat bogs contain up to 155 million tonnes of dry peat covering a combined area of 50 000 hectares. About 77% of peat reserves are near Akanyaru and Nyabarongo rivers and the Rwabusoro Plains.

Explore

Thermal

Currently, there are 10 thermal power plants in Rwanda including those using diesel and those using other fuels such as Methane and Peat. These power plants are currently generating generating 53.6% of the total electricity in Rwanda. Efforts were made to develop the energy production aim at stopping the use of of Diesel in the energy mix as it is the mos…

Explore

Geothermal

Rwanda may have geothermal potential which is manifested in the form of hot springs (Fig. 1) and hosts two prospective zones for geothermal energy exploration: the first zone in the north-western region (Gisenyi, Karisimbi, and Kinigi) which is associated with volcanoes and the second zone in the southern region (Bugarama) associated with faults in the Ea…

Explore

Power Plants

Values are preserved from the official REG source table and are undergoing technical review.

Plant NameTechnologyGridInstalled CapacityOwnershipYear
AgatobweHydropowerOff-grid0.39 MWCARERA-EDERER/ IPP2010
CyimbiliHydropowerOn-grid0.3 MWENERGICOTEL LTD/ PPP2011
GasekeHydropowerOn-grid0.5 MWNOVEL ENERGY LTD /IPP2016
GashashiHydropowerOn-grid0.28 MWPRIME ENERGY LTD/ PPP2013
Giciye IIIHydropowerOn-grid9.8 MWRMT-Energy Development Ltd2020
Giciye1HydropowerOn-grid4 MWRMT LTD/ IPP2014
Giciye2HydropowerOn-grid4 MWRMT LTD/ IPP2016
GihiraHydropowerOn-grid1.8 MWRMT LTD/ PPP1984
GisenyiHydropowerOn-grid1.7 MWPRIME ENERGY LTD/ PPP1957
JanjaHydropowerOn-grid0.2 MWRWANDA ENERGY UK LTD/ PPP2012
KeyaHydropowerOn-grid2.2 MWENERGICOTEL LTD/ PPP2011
KigasaHydropowerOn-grid0.272 MWLED Solutions2020
MazimeruHydropowerOn-grid0.5 MWENNY LTD / IPP2012
Mukugu Pico power plantHydropowerOff-grid0.016 MWHanded over to REG in Jan/20202020
Mukungwa 1HydropowerOn-grid12 MWREG/GoR1982
Mukungwa 2HydropowerOn-grid3.6 MWPRIME ENERGY LTD/ PPP2013
MurundaHydropowerOn-grid0.1 MWREPRO LTD/ IPP2010
MusararaHydropowerOn-grid0.4 MWAMAHORO ENERGY LTD/IPP2013
MutoboHydropowerOn-grid0.2 MWREPRO LTD/ IPP2009
NkoraHydropowerOn-grid0.68 MWENERGICOTEL LTD/ PPP2011
Nshili1HydropowerOn-grid0.4 MWREG /GoR2012
NtarukaHydropowerOn-grid11.25 MWREG/ GoR1959
NyabahangaHydropowerOn-grid0.2 MWREG/GOR2012
Nyabarongo IHydropowerOn-grid28 MWREG/ GoR2014
Nyamyotsi IHydropowerOn-grid0.1 MWENERGICOTEL LTD/ PPP2007
Nyamyotsi IIHydropowerOn-grid0.1 MWENERGICOTEL LTD/ PPP2011
NyirabuhombohomboHydropowerOff-grid0.65 MWRWANDA ENERGY UK LTD/ PPP2013
NyirantarukoHydropowerOn-grid1.84 MWNyirantaruko Hydropower Ltd2020
RubagabagaHydropowerOn-grid0.45 MW2019
RugeziHydropowerOn-grid2.6 MWRMT LTD/PPP2011
Rukarara 1HydropowerOn-grid9 MWNGALI ENERGY LTD/ PPP2010
Rukarara 2HydropowerOn-grid2.2 MWPRIME ENERGY LTD/ PPP2014
Rukarara V & MushishitoHydropowerOn-grid5 MWREFAD2019
Ruzizi 1HydropowerOn-grid4.1 MWSNEL/ IPP1958
Ruzizi 2HydropowerOn-grid12 MWSNELAC/ PPP1989
Rwaza-MukoHydropowerOn-grid2.6 MWRwaza-Muko SPV2018
GigaWatt /RwamaganaSolarOn-grid8.5 MWGIGAWATT GLOBAL/ IPP2015
JaliSolarOn-grid0.25 MWMAINZ/ IPP—
Nasho SolarSolarOn-grid3.3 MWREG/GoR2017
GishomaThermalOn-grid15 MWREG/GoR2016
Hakan PTPThermalOn-grid35 MWREG/GoR2022
Jabana 1ThermalOn-grid7.8 MWREG/GoR—
Jabana 2ThermalOn-grid21 MWREG /GoR—
Kibuye Gaz methaneThermalOn-grid26.19 MWKIVUWATT LTD / IPP2015
KP1ThermalOn-grid3.6 MWSYMBION POWER / PPP2012
SoEnergy LTD ( Birembo)ThermalOn-grid10 MWSoEnergy / IPP2017
SoEnergy LTD ( MUKUNGWA)ThermalOn-grid10 MWSoEnergy / IPP2017
SoEnergy LTD ( SEZ)ThermalOn-grid10 MWSoEnergy / IPP2017
UETCLThermalOn-grid2 MW—

Related Projects

Transmission

110 kV Gasogi-KSEZ

The project consists of building a 2.2km long 110KV transmission line linking Gasogi substation to Kigali Special Economic Zone

View project