Official page content
110 kV Jabana-Mt Kigali-Gahanga
| Project Category | Transmission |
| Project Name | 110 kV Jabana-Mt Kigali-Gahanga |
| Donor/Funder | European Union |
| Effectiveness Date | 19 Aug 2016 |
| Closure Date | 22 Dec 2017 |
| Status | Completed |
Scope
The project constists of construction of a 27 km long 110KV transmission line linking Jabana, Mont Kigali and Gahanga to ensure sustainability of power supply in the City of Kigali.
Geographic Coverage
Jabana - Gahanga
Public summary
The project constists of construction of a 27 km long 110KV transmission line linking Jabana, Mont Kigali and Gahanga to ensure sustainability of power supply in the City of Kigali.
Project category
Transmission
Project status
Completed
Donor / funder
European Union
Project scope
The project constists of construction of a 27 km long 110KV transmission line linking Jabana, Mont Kigali and Gahanga to ensure sustainability of power supply in the City of Kigali.
Effectiveness date
Closure date
Geographic coverage
Jabana - Gahanga
Official project image
110 kV Jabana-Mt Kigali-Gahanga