Kigali Network Strenghening 2
| Project Category | Transmission , Medium Voltage |
| Project Name | Kigali Network Strenghening 2 |
| Donor/Funder | World Bank |
| Effectiveness Date | 01 Mar 2018 |
| Closure Date | 31 Jan 2019 |
| Status | Ongoing |
Scope
Rehabilitation of MV underground cable within Kigali city Centre, construction of a 1.5km four circuit overhead line between Gikondo and KBC; replacement of MV underground cables from KBC to Christus.
This Project is divided in 3 lots:
- 1st lot: Supply of underground cables
- 2nd lot: Design supply and installation for the overhead line.
- 3rd lot: installation of under ground cables
Geographic Coverage
Kigali City
Public summary
Rehabilitation of MV underground cable within Kigali city Centre, construction of a 1.5km four circuit overhead line between Gikondo and KBC; replacement of MV underground cables from KBC to Christus. This Project is divided in 3 lots:
Project category
Transmission , Medium Voltage
Project status
Ongoing
Donor / funder
World Bank
Project scope
Rehabilitation of MV underground cable within Kigali city Centre, construction of a 1.5km four circuit overhead line between Gikondo and KBC; replacement of MV underground cables from KBC to Christus.