110 kV Gasogi-KSEZ
The project consists of building a 2.2km long 110KV transmission line linking Gasogi substation to Kigali Special Economic Zone
110 kV Gishoma-Bugarama
This is a 13 km long 110 KV transmission line linking Gishoma Power plant to Bugarama Substation.
110 kV Jabana-Mt Kigali-Gahanga
The project constists of construction of a 27 km long 110KV transmission line linking Jabana, Mont Kigali and Gahanga to ensure sustainability of power supply in the City of Kigali.
110 kV Ntendezi–Bugarama
This project included the construction of a 17.5 km transmission line linking Ntendezi and Bugarama with the associated substations. This line transmission line will ensure power stability in the West of Rwanda and CIMERWA factory
110 kV Nyabarongo 1 HPP-Kilinda
This is a line of 28 km linking Nyabarongo Hydropwer to Kilinda Substation. It was completed in 2014.
110 kV Rukarara-Kilinda
This is 110 KV transmission line with a length of 31.5km. It evacuates power from Rukarara Hydropower plant to Kilinda Substation
110 kV Single Circuit: Mukungwa-Nyabihu
The project consists of construction of 29km long transmission line linking Mukungwa to Nyabihu
110kV Jabana-Mt. Kigali-Gahanga and associated substations
The project consists of building a 27km long 110KV transmission line linking Jabana, Mont Kigali up to Gahanga Substation.
110kV Rulindo-Gabiro-Musha
This 110 KV line with its associated substations (Rulindo and Gabiro) connects Rulindo, Gabiro and Musha (Rwamagana) on a distance of 119km.
220 KV Bwishyura-Kigoma-Rwabusoro
The project consists of building a 62 km long 220KV transmission line linking Bwishyura, Kigoma and Rwabusoro.
220 kV Kigoma-Butare-Ngozi-Gitega
The project consists of construction of 62km long transmission line from Kigom, Butare, Ngozi and Gitega. This 220KV line will facilitate interconnection and exchange electricity between Rwanda and Burundi
220 kV Mirama-Shango
This is a 220 KV line connecting Rwanda to Uganda with a length of 93.5. It will facilitate the interconnection between the two countries.
220 kV Rusumo- Bugesera-Shango
The project consists of construction of a 119km long 220KV transmission line with its associate substations which will evacuate power from Rusumo Hydropower Plant (under construction) to Bugesera up to Shango
220 kV Shango-Rubavu-Bwishyura-Kibuye
This is a 220 KV transmission line linking Shango, Rubavu, Bwishyura and Kibuye on a distance of 180km.
220/110 kV Mamba-Rwabusoro-(110kV) Bugesera- Gahanga
The project consists of building a 84.5 km long transmission line evacuating power from Hakan Peat to Power plant in Gisagara District up to Gahanga in through Rwabusoro and Bugesera substations
EASSDP- Electricity Access Scale up and sector wide Approach development project. CR N° 4651-RW
EASSDP- Electricity Access Scale up and sector wide Approach development project. CR N° 4651-RW information published by Rwanda Energy Group.
Electricity Access ScaIe-Up Project Loan Agreement N°1293P”
Electricity Access ScaIe-Up Project Loan Agreement N°1293P” information published by Rwanda Energy Group.
Gishoma 15 MW Peat to Power Project
Since 2010, the Government started development of the 15MW peat power plant in Gishoma, Rusizi District, to reduce electricity deficit which the country was facing and to coincide with a significant growth of electricity demand observed in the region as a result of the expansion of the local cement factory and country development.
Hakan Quantum Power Project
YUMN Ltd. is developing an 80 MW peat fired power plant in South Akanyaru prospect in Gisagara District and the project is to be developed as Public Private Partnership (PPP). On Feb 10, 2016, Amendment and Restatement Deeds for Power Purchase Agreement, Concession Agreement and Government Guarantee have been signed. Since February 2017 the project is und…
Improving Access to reliable on Grid Electricity Services for Households and Priority public institutions - BE1EARP
Improving Access to reliable on Grid Electricity Services for Households and Priority public institutions - BE1EARP information published by Rwanda Energy Group.
Improving Access to reliable on Grid Electricity Services for Households and Priority public institutions - BE2EARP
Improving Access to reliable on Grid Electricity Services for Households and Priority public institutions - BE2EARP information published by Rwanda Energy Group.
Improving Access to reliable on Grid Electricity Services for Households and Priority public institutions - BE3EARP
Improving Access to reliable on Grid Electricity Services for Households and Priority public institutions - BE3EARP information published by Rwanda Energy Group.
Increasing Access to Electricity to Some Areas in Rwanda
Grid extention by 194 km of Medium Voltage lines and 489 km of Low Voltage lines and 133 distribution transformers
Kibuye Power 1
pilot project located in Karongi district, has been generating around 3MW of electrical power with the design capacity of 3.6 MW; In 2016 Symbion Power acquired the KP1 barge and onshore facility.Symbion through the liquidation process and is now mobilizing funds to revive the plant and scale it up to 25 MW.
Kigali Network Strenghening 1 - 1
Improved stability of power supply in Bugesera and parts of Kigali by replacing a10MVA transformer by a 20MVA at Mont Kigali substation
Kigali Network Strenghening 1 - 2
Kigali distribution network reinforced (upgrade, rehabilitation and integration to SCADA of 6 identified substations )
Kigali Network Strenghening 1 - 3
Kigali distribution network reinforced (upgrade, rehabilitation and integration to SCADA of 11 identified substations )
Kigali Network Strenghening 2
Rehabilitation of MV underground cable within Kigali city Centre, construction of a 1.5km four circuit overhead line between Gikondo and KBC; replacement of MV underground cables from KBC to Christus. This Project is divided in 3 lots:
Kigali Ring I
The project consists of construction of 27km of 110kV transmission line from Jabana to Gahanga via Mont Kigali, construction of 110/30/15kV, 40MVA substation at Mont Kigali, 110/15kV; 20MVA substation at Gahanga; addition of a second transformer at Birembo (20MVA)
Kigali Ring II
Installation of reactive power compensators (capacitor banks) at MV side of the following substations,: Gikondo, Jabana and Birembo. Each substation with 4.5MVAr;
KivuWatt Project Phase I
A subsidiary of Contour Global (US-based Company) entered into commercial operations since 31st December 2015 and operates at base load with a nominal gross capacity of 26 MW.
Nyabarongo II Multipurpose project
Nyabarongo II (43.5MW) is a multipurpose project expected to cater for water supply, irrigation as well as electrical power generation. The project is also envisaged to mitigate the perpetual flooding downstream of the Nyabarongo River that has proved to be hazardous in the recent years. The project is fully funded by the Government of Rwanda is expected…
Rural electrification Project in Burera and Nyagatare Districts
The project will extend the national grid by 221.4 km of MV lines and 393.15 km of LV lines. A total of 18761 new connections will be made in Burera and Nyagatare Districts
Rusumo Falls Hydro Power Project
The project is being developed under NELSAP umbrella for Rwanda, Burundi and Tanzania funded by the World Bank. Rusumo falls Hydropower Project is planned to generate 80 MW and the power output will be shared equally by three countries. The project consists of concrete dam with crest length of 150m,Headrace Tunnel of 460m and a surface power station with…
Ruzizi III
Rusizi III Hydropower (145MW) construction project is supported by the World Bank, EU, AfDB among others with an expected investment capital of $450 million and is expected to be completed by 2024. The project is being developed under CEPGL umbrella for Rwanda, Burundi and DRC. Rusizi III hydropower project planned to generate 147MW and the power output w…
Rwanda Electricity Sector Strengthening Project
Rwanda Electricity Sector Strengthening Project information published by Rwanda Energy Group.
Scaling- up energy access Project
(a) 25,438 households connected to national electricity, (b)179 schools, 29 health centers and 25 sector and cells administration offices with access to electricity in the project area, by (i) constructing 464Km of MV distribution lines and (ii) 710 Km of LV network.
Shema Power Lake Kivu
Shema Power Lake Kivu Limited (SPLK ltd) signed a 25-year power purchase agreement (PPA) with the Rwanda Energy Group (REG) for a 56 MW net power output from methane gas. The Power plant will be located on Nyamyumba sector in Rubavu District. The first barge will provide 14 MW of electricity 15 months after the project reaches Financial Close.
REG Projects
Increasing Access to Electricity to Some Areas in Rwanda
Grid extention by 194 km of Medium Voltage lines and 489 km of Low Voltage lines and 133 distribution transformers
View projectHakan Quantum Power Project
YUMN Ltd. is developing an 80 MW peat fired power plant in South Akanyaru prospect in Gisagara District and the project is to be developed as Public Private Partnership (PPP). On Feb 10, 2016, Amendment and Restatement Deeds for Power Purchase Agreement, Concession Agreement and Government Guarantee have been signed. Since February 2017 the project is und…
View projectGishoma 15 MW Peat to Power Project
Since 2010, the Government started development of the 15MW peat power plant in Gishoma, Rusizi District, to reduce electricity deficit which the country was facing and to coincide with a significant growth of electricity demand observed in the region as a result of the expansion of the local cement factory and country development.
View projectNyabarongo II Multipurpose project
Nyabarongo II (43.5MW) is a multipurpose project expected to cater for water supply, irrigation as well as electrical power generation. The project is also envisaged to mitigate the perpetual flooding downstream of the Nyabarongo River that has proved to be hazardous in the recent years. The project is fully funded by the Government of Rwanda is expected…
View projectRwanda Electricity Sector Strengthening Project
Rwanda Electricity Sector Strengthening Project information published by Rwanda Energy Group.
View projectImproving Access to reliable on Grid Electricity Services for Households and Priority public institutions - BE3EARP
Improving Access to reliable on Grid Electricity Services for Households and Priority public institutions - BE3EARP information published by Rwanda Energy Group.
View projectImproving Access to reliable on Grid Electricity Services for Households and Priority public institutions - BE2EARP
Improving Access to reliable on Grid Electricity Services for Households and Priority public institutions - BE2EARP information published by Rwanda Energy Group.
View projectImproving Access to reliable on Grid Electricity Services for Households and Priority public institutions - BE1EARP
Improving Access to reliable on Grid Electricity Services for Households and Priority public institutions - BE1EARP information published by Rwanda Energy Group.
View projectScaling- up energy access Project
(a) 25,438 households connected to national electricity, (b)179 schools, 29 health centers and 25 sector and cells administration offices with access to electricity in the project area, by (i) constructing 464Km of MV distribution lines and (ii) 710 Km of LV network.
View projectRural electrification Project in Burera and Nyagatare Districts
The project will extend the national grid by 221.4 km of MV lines and 393.15 km of LV lines. A total of 18761 new connections will be made in Burera and Nyagatare Districts
View projectKivuWatt Project Phase I
A subsidiary of Contour Global (US-based Company) entered into commercial operations since 31st December 2015 and operates at base load with a nominal gross capacity of 26 MW.
View projectEASSDP- Electricity Access Scale up and sector wide Approach development project. CR N° 4651-RW
EASSDP- Electricity Access Scale up and sector wide Approach development project. CR N° 4651-RW information published by Rwanda Energy Group.
View projectElectricity Access ScaIe-Up Project Loan Agreement N°1293P”
Electricity Access ScaIe-Up Project Loan Agreement N°1293P” information published by Rwanda Energy Group.
View projectKigali Network Strenghening 2
Rehabilitation of MV underground cable within Kigali city Centre, construction of a 1.5km four circuit overhead line between Gikondo and KBC; replacement of MV underground cables from KBC to Christus. This Project is divided in 3 lots:
View projectKigali Network Strenghening 1 - 1
Improved stability of power supply in Bugesera and parts of Kigali by replacing a10MVA transformer by a 20MVA at Mont Kigali substation
View projectKigali Network Strenghening 1 - 2
Kigali distribution network reinforced (upgrade, rehabilitation and integration to SCADA of 6 identified substations )
View projectKigali Network Strenghening 1 - 3
Kigali distribution network reinforced (upgrade, rehabilitation and integration to SCADA of 11 identified substations )
View projectKigali Ring II
Installation of reactive power compensators (capacitor banks) at MV side of the following substations,: Gikondo, Jabana and Birembo. Each substation with 4.5MVAr;
View projectKigali Ring I
The project consists of construction of 27km of 110kV transmission line from Jabana to Gahanga via Mont Kigali, construction of 110/30/15kV, 40MVA substation at Mont Kigali, 110/15kV; 20MVA substation at Gahanga; addition of a second transformer at Birembo (20MVA)
View project110 kV Gishoma-Bugarama
This is a 13 km long 110 KV transmission line linking Gishoma Power plant to Bugarama Substation.
View project110 kV Gasogi-KSEZ
The project consists of building a 2.2km long 110KV transmission line linking Gasogi substation to Kigali Special Economic Zone
View project110 kV Single Circuit: Mukungwa-Nyabihu
The project consists of construction of 29km long transmission line linking Mukungwa to Nyabihu
View project220 KV Bwishyura-Kigoma-Rwabusoro
The project consists of building a 62 km long 220KV transmission line linking Bwishyura, Kigoma and Rwabusoro.
View project110 kV Rukarara-Kilinda
This is 110 KV transmission line with a length of 31.5km. It evacuates power from Rukarara Hydropower plant to Kilinda Substation
View project220/110 kV Mamba-Rwabusoro-(110kV) Bugesera- Gahanga
The project consists of building a 84.5 km long transmission line evacuating power from Hakan Peat to Power plant in Gisagara District up to Gahanga in through Rwabusoro and Bugesera substations
View project220 kV Kigoma-Butare-Ngozi-Gitega
The project consists of construction of 62km long transmission line from Kigom, Butare, Ngozi and Gitega. This 220KV line will facilitate interconnection and exchange electricity between Rwanda and Burundi
View project220 kV Rusumo- Bugesera-Shango
The project consists of construction of a 119km long 220KV transmission line with its associate substations which will evacuate power from Rusumo Hydropower Plant (under construction) to Bugesera up to Shango
View project110 kV Jabana-Mt Kigali-Gahanga
The project constists of construction of a 27 km long 110KV transmission line linking Jabana, Mont Kigali and Gahanga to ensure sustainability of power supply in the City of Kigali.
View project110kV Rulindo-Gabiro-Musha
This 110 KV line with its associated substations (Rulindo and Gabiro) connects Rulindo, Gabiro and Musha (Rwamagana) on a distance of 119km.
View project110kV Jabana-Mt. Kigali-Gahanga and associated substations
The project consists of building a 27km long 110KV transmission line linking Jabana, Mont Kigali up to Gahanga Substation.
View project220 kV Mirama-Shango
This is a 220 KV line connecting Rwanda to Uganda with a length of 93.5. It will facilitate the interconnection between the two countries.
View project220 kV Shango-Rubavu-Bwishyura-Kibuye
This is a 220 KV transmission line linking Shango, Rubavu, Bwishyura and Kibuye on a distance of 180km.
View project110 kV Nyabarongo 1 HPP-Kilinda
This is a line of 28 km linking Nyabarongo Hydropwer to Kilinda Substation. It was completed in 2014.
View project110 kV Ntendezi–Bugarama
This project included the construction of a 17.5 km transmission line linking Ntendezi and Bugarama with the associated substations. This line transmission line will ensure power stability in the West of Rwanda and CIMERWA factory
View projectRusumo Falls Hydro Power Project
The project is being developed under NELSAP umbrella for Rwanda, Burundi and Tanzania funded by the World Bank. Rusumo falls Hydropower Project is planned to generate 80 MW and the power output will be shared equally by three countries. The project consists of concrete dam with crest length of 150m,Headrace Tunnel of 460m and a surface power station with…
View projectRuzizi III
Rusizi III Hydropower (145MW) construction project is supported by the World Bank, EU, AfDB among others with an expected investment capital of $450 million and is expected to be completed by 2024. The project is being developed under CEPGL umbrella for Rwanda, Burundi and DRC. Rusizi III hydropower project planned to generate 147MW and the power output w…
View projectShema Power Lake Kivu
Shema Power Lake Kivu Limited (SPLK ltd) signed a 25-year power purchase agreement (PPA) with the Rwanda Energy Group (REG) for a 56 MW net power output from methane gas. The Power plant will be located on Nyamyumba sector in Rubavu District. The first barge will provide 14 MW of electricity 15 months after the project reaches Financial Close.
View projectKibuye Power 1
pilot project located in Karongi district, has been generating around 3MW of electrical power with the design capacity of 3.6 MW; In 2016 Symbion Power acquired the KP1 barge and onshore facility.Symbion through the liquidation process and is now mobilizing funds to revive the plant and scale it up to 25 MW.
View project